Roofing work was completed on 31st August.  The loft insulation has been considerably increased and air vents installed to increase ventilation in the loft space.  Gutters on both sides were replaced.  Replacing the red ridge tiles proved to be too costly so new black ones were installed. 
Users of the Village Hall are requested to make sure the lights are out when they leave the building, as sometimes they are left on.